Residential Construction Template

15 tasks~6 months estimatedConstruction

Single-family home construction from design to move-in

What's Included

This template contains 15 tasks with built-in dependencies, milestones, and realistic duration estimates. Each task includes a description so your team knows exactly what needs to happen.

  1. 1
    Project Kickoff
    Align stakeholders on design requirements, budget, and construction timeline
    Milestone
  2. 2
    Architectural Design and Client Approval
    Develop architectural plans, elevations, and floor plans for client review and sign-off
    2 weeks
  3. 3
    Finalize Construction Documents
    Complete engineering drawings, structural calculations, and MEP plans
    1 week
  4. 4
    Obtain Building Permits
    Submit construction plans to local authority for zoning, building, and utility permits
    4 weeks
  5. 5
    Site Preparation and Grading
    Clear land, excavate, and install temporary site utilities
    1 week
  6. 6
    Foundation and Slab Construction
    Excavate footings, pour concrete foundation and slab, and install drainage
    2 weeks
  7. 7
    Framing and Roofing
    Erect structural framing (walls, floors, roof) and install roofing materials
    3 weeks
  8. 8
    Rough-In Electrical and Plumbing
    Install electrical conduits, plumbing pipes, and HVAC ductwork within structure
    2 weeks
  9. 9
    Insulation and Drywall Installation
    Install insulation, vapor barriers, and drywall throughout the home
    2 weeks
  10. 10
    Interior Finishes (Floors, Walls, Trim)
    Install flooring, paint walls, and finish interior trim and cabinetry
    3 weeks
  11. 11
    Exterior Finishes (Siding, Windows, Doors)
    Install siding, windows, doors, and exterior trim
    2 weeks
  12. 12
    Interior Fixtures and Appliances
    Install plumbing fixtures, lighting, kitchen appliances, and HVAC controls
    1 week
  13. 13
    Final Inspections and Punch List
    Conduct building inspections and address any required corrections
    1 week
  14. 14
    Final Cleaning and Handover
    Perform deep cleaning and deliver completed home to client
    5 days
  15. 15
    Project Complete
    Formal handover of keys, warranties, and maintenance documentation
    Milestone

Who This Is For

Custom home builders and residential contractors use this template to manage the full homebuilding process from architectural design to final walkthrough. It includes realistic timelines for permit acquisition, parallel interior and exterior finish work, and the critical punch list phase.

Why Use LoopGantt

Home construction involves weather delays, permit hold-ups, and subcontractor scheduling conflicts. LoopGantt lets you quickly adjust timelines when reality diverges from the plan, automatically pushing downstream phases and giving homeowners a realistic move-in date at all times.