Residential Construction Template
Single-family home construction from design to move-in
What's Included
This template contains 15 tasks with built-in dependencies, milestones, and realistic duration estimates. Each task includes a description so your team knows exactly what needs to happen.
- 1Project KickoffAlign stakeholders on design requirements, budget, and construction timelineMilestone
- 2Architectural Design and Client ApprovalDevelop architectural plans, elevations, and floor plans for client review and sign-off2 weeks
- 3Finalize Construction DocumentsComplete engineering drawings, structural calculations, and MEP plans1 week
- 4Obtain Building PermitsSubmit construction plans to local authority for zoning, building, and utility permits4 weeks
- 5Site Preparation and GradingClear land, excavate, and install temporary site utilities1 week
- 6Foundation and Slab ConstructionExcavate footings, pour concrete foundation and slab, and install drainage2 weeks
- 7Framing and RoofingErect structural framing (walls, floors, roof) and install roofing materials3 weeks
- 8Rough-In Electrical and PlumbingInstall electrical conduits, plumbing pipes, and HVAC ductwork within structure2 weeks
- 9Insulation and Drywall InstallationInstall insulation, vapor barriers, and drywall throughout the home2 weeks
- 10Interior Finishes (Floors, Walls, Trim)Install flooring, paint walls, and finish interior trim and cabinetry3 weeks
- 11Exterior Finishes (Siding, Windows, Doors)Install siding, windows, doors, and exterior trim2 weeks
- 12Interior Fixtures and AppliancesInstall plumbing fixtures, lighting, kitchen appliances, and HVAC controls1 week
- 13Final Inspections and Punch ListConduct building inspections and address any required corrections1 week
- 14Final Cleaning and HandoverPerform deep cleaning and deliver completed home to client5 days
- 15Project CompleteFormal handover of keys, warranties, and maintenance documentationMilestone
Who This Is For
Custom home builders and residential contractors use this template to manage the full homebuilding process from architectural design to final walkthrough. It includes realistic timelines for permit acquisition, parallel interior and exterior finish work, and the critical punch list phase.
Why Use LoopGantt
Home construction involves weather delays, permit hold-ups, and subcontractor scheduling conflicts. LoopGantt lets you quickly adjust timelines when reality diverges from the plan, automatically pushing downstream phases and giving homeowners a realistic move-in date at all times.