Office Renovation Template

13 tasks~7 weeks estimatedConstruction

Complete office space renovation and redesign

What's Included

This template contains 13 tasks with built-in dependencies, milestones, and realistic duration estimates. Each task includes a description so your team knows exactly what needs to happen.

  1. 1
    Project Kickoff
    Align stakeholders on goals, scope, and timeline
    Milestone
  2. 2
    Planning and Design
    Create architectural plans, space layout, and material selections
    5 days
  3. 3
    Stakeholder Design Review
    Formal review of design plans with stakeholders
    1 day
  4. 4
    Procurement of Materials
    Ordering and scheduling delivery of renovation materials
    5 days
  5. 5
    Obtain Permits
    Submit and secure all required construction permits
    1 week
  6. 6
    Demolition
    Remove existing walls, flooring, and non-essential structures
    4 days
  7. 7
    Structural Work
    Modify load-bearing walls and reinforce foundations
    5 days
  8. 8
    Electrical/Plumbing
    Install new wiring, circuits, and plumbing systems
    1 week
  9. 9
    Drywall and Insulation
    Install drywall, insulation, and acoustic treatments
    4 days
  10. 10
    Finishes (Flooring, Painting)
    Install new flooring, paint walls, and apply finishes
    1 week
  11. 11
    Furniture Installation
    Set up office furniture, cubicles, and equipment
    3 days
  12. 12
    Final Inspections
    Conduct safety, electrical, and building code inspections
    2 days
  13. 13
    Project Complete
    Official handover and sign-off on renovated space
    Milestone

Who This Is For

Facilities managers and office operations leads use this template to manage office renovations with minimal business disruption. It sequences demolition, structural, and finish work logically and includes time for permits and inspections, helping teams plan around business continuity needs.

Why Use LoopGantt

Office renovations have a hard constraint: you need the space back by a specific date. LoopGantt counts backward from your move-in deadline and shows whether your current plan is achievable, highlighting any phases that need more crew or overtime to stay on track.