Commercial Construction Template

14 tasks~5 months estimatedConstruction

Commercial building construction from permits to completion

What's Included

This template contains 14 tasks with built-in dependencies, milestones, and realistic duration estimates. Each task includes a description so your team knows exactly what needs to happen.

  1. 1
    Project Kickoff
    Align stakeholders on goals, scope, and timeline
    Milestone
  2. 2
    Design Review and Engineering Plans
    Finalize architectural/engineering designs and obtain design approvals
    3 weeks
  3. 3
    Secure Building Permits
    Submit plans to local authority and obtain all required construction permits
    4 weeks
  4. 4
    Utility Connections
    Coordinate and install temporary utilities for construction site
    1 week
  5. 5
    Site Preparation
    Clear site, grade land, and install temporary utilities
    1 week
  6. 6
    Stakeholder Approval Gate
    Formal approval of construction plans by stakeholders
    3 days
  7. 7
    Foundation Work
    Excavate, pour footings, and complete foundation system
    1 week
  8. 8
    Structural Framing
    Erect steel or concrete framework of the building
    2 weeks
  9. 9
    Roofing and Exterior Shell
    Install roofing system and complete exterior envelope
    1 week
  10. 10
    MEP Installations
    Install mechanical, electrical, and plumbing systems
    6 weeks
  11. 11
    Interior Partitions
    Construct interior walls and ceiling systems
    1 week
  12. 12
    Finish Work (Drywall, Flooring, Paint)
    Install finish materials throughout the building
    4 weeks
  13. 13
    Final Inspections
    Conduct all required final code and safety inspections
    5 days
  14. 14
    Project Complete
    Hand over building to client and close contracts
    Milestone

Who This Is For

General contractors and construction project managers use this template to plan commercial building projects from permit acquisition through final inspections. It captures the sequential nature of construction phases and accounts for long-lead items like permits and MEP installations.

Why Use LoopGantt

Construction projects have strict sequential dependencies where foundation work must complete before framing can begin. LoopGantt enforces these dependencies automatically and gives you a clear critical path view, making it easy to see which delays will push back your completion date and which have float.