Hitos y fechas deseadas

La versión en inglés de este artículo es la oficial. El contenido localizado llegará en una próxima actualización.

Milestones are the punctuation marks of your project plan. They don't represent work — they represent decisions made, deliverables handed off, and gates passed. A plan without milestones is hard to communicate and hard to control.

What makes a good milestone?

A milestone should have a clear, binary outcome: it either happened or it didn't. Avoid vague milestones like "Development complete" — there is always one more bug. Instead use: "Build deployed to staging and smoke-tested."

Strong milestone examples:

  • Project Kickoff (agreement to begin)
  • Requirements Sign-off (written approval from stakeholders)
  • Design Approved (final mockups signed off)
  • Code Freeze (no new features, only bug fixes)
  • Beta Released (shipped to test users)
  • Go Live (publicly available)
  • Post-Launch Review Held

Milestones in LoopGantt

A milestone is a task with duration = 0. It appears as a diamond symbol on the Gantt timeline. To create one:

  1. Add a task as normal.
  2. Set the duration to 0, or toggle the Milestone switch in the task editor.
  3. The task bar turns into a diamond (◆) on the Gantt.

Milestones can be assigned dependenciesjust like regular tasks. A common pattern: link the last task of a phase to a milestone that gates the next phase. This creates a clear "phase gate" in your plan.

Desired Date — schedule a task for a specific date

A Desired Datetells the scheduler when you want a task to start. The scheduler uses this date as long as it doesn't conflict with dependencies.

How it works:

  • No dependencies: The task starts on the desired date.
  • With dependencies, desired date is later: The task is delayed to the desired date — useful for intentionally pushing a task later within its available float (slack time).
  • With dependencies, desired date is earlier: The desired date is ignored. A task cannot start before its predecessors allow.

Use desired dates for:

  • Tasks tied to a fixed external date (conference, launch, regulatory deadline)
  • Delaying a task to a specific day even though it could start earlier
  • Milestones with a known target (e.g., "Go Live on July 31")
Tip:Use milestones at the end of each phase as "gates." Link the first task of the next phase to that milestone (FS dependency). This makes it impossible to start Phase 2 until Phase 1 is formally closed — exactly how phase-gated methodologies work.