Dependencias entre tareas, explicadas

La versión en inglés de este artículo es la oficial. El contenido localizado llegará en una próxima actualización.

Dependencies define the logical order of work. They are the backbone of any Gantt chart and the reason scheduling software exists — manually tracking how a delay in one task ripples through 50 others is impossible without them.

Why dependencies matter

When you link tasks with dependencies, LoopGantt becomes a scheduling engine, not just a calendar. Change a task duration or move a date and the entire downstream schedule recalculates instantly. This is called schedule cascade and it saves hours of manual re-planning after the inevitable scope changes.

Dependencies also reveal your project's critical path — the longest chain of dependent tasks. Any delay on the critical path delays the project end date. Tasks not on the critical path have float (slack) — they can slip without affecting the delivery date.

The four dependency types

FS — Finish-to-Start (most common)

Task A ████████
                Task B ████████
Task B cannot start until Task A finishes.

Use for sequential work: "Write the report" → "Review the report". This is the default and covers ~80% of real-world dependencies.

SS — Start-to-Start

Task A ████████████
   Task B    ████████
Task B cannot start until Task A starts.

Use for parallel work that can begin together but must be coordinated. Example: "Architecture design" and "API specification" can start at the same time, but the spec depends on architecture being underway.

Add a lag(SS+3) to say "B starts 3 days after A starts" — useful when you need A to be partially done before B begins.

FF — Finish-to-Finish

Task A ████████████
      Task B ████████
Task B cannot finish until Task A finishes.

Use when two tasks must wrap up together. Example: "QA testing" and "Beta testing" should end at the same time so the team can move to submission together.

SF — Start-to-Finish (rare)

             Task A ████████
Task B ████████
Task B cannot finish until Task A starts.

The rarest type. Useful in just-in-time and shift-handover scenarios. Example: the night-shift worker (B) cannot leave until the day-shift worker (A) arrives. In most software projects, you will rarely need SF.

Lag and lead time

Every dependency can have a lag (positive number) or lead time (negative number):

NotationMeaning
FS+2B starts 2 days after A finishes
FS-1B starts 1 day before A finishes (overlap)
SS+5B starts 5 days after A starts
FF+0B finishes exactly when A finishes

Lead time (negative lag) lets you model realistic parallel work — for example, starting integration testing 2 days before development officially finishes.

Rules in LoopGantt

  • Phases cannot have dependencies. Link the tasks inside phases instead.
  • Circular dependencies (A → B → A) are automatically detected and rejected.
  • A task can have multiple predecessors — it will start only after all predecessors satisfy their constraints.

How to add a dependency

  1. Click the successor task to open the task editor.
  2. Go to the Dependencies tab.
  3. Click + Add Predecessor.
  4. Select the predecessor task, choose the type (FS/SS/FF/SF), and optionally set lag days.
  5. Click Save. The chart reschedules immediately.

You can also drag a dependency line directly on the Gantt: hover over the right edge of a bar until the connector icon appears, then drag to the target task.