Skip to main content

Web Application MVP Template

16 tasks~7 weeks estimatedSoftware Development

Build a minimum viable product web application from scratch

What's Included

This template contains 16 tasks with built-in dependencies, milestones, and realistic duration estimates. Each task includes a description so your team knows exactly what needs to happen.

  1. 1
    Project Kickoff
    Align stakeholders on MVP scope, requirements, and success criteria
    Milestone
  2. 2
    Discovery Phase
    Conduct stakeholder interviews, define MVP scope, create user stories, and complete competitor analysis
    5 days
  3. 3
    UI/UX Design
    Create wireframes, user flows, and interactive mockups for core features
    1 week
  4. 4
    Design Review & Approval
    Present and finalize design assets with stakeholders
    2 days
  5. 5
    Front-End Development
    Implement client-side interfaces using HTML/CSS/JavaScript framework
    6 days
  6. 6
    Back-End Development
    Develop server-side logic, APIs, and database architecture
    6 days
  7. 7
    System Integration
    Connect front-end with back-end, implement core feature integrations
    3 days
  8. 8
    Development Review
    Verify completion of MVP development phase
    Milestone
  9. 9
    Unit Testing
    Execute unit tests for both front-end and back-end components
    3 days
  10. 10
    Integration Testing
    Verify cross-component functionality and API interactions
    3 days
  11. 11
    User Acceptance Testing (UAT)
    Conduct stakeholder testing with real user scenarios
    4 days
  12. 12
    Bug Fixing & QA
    Resolve issues identified in testing phases
    5 days
  13. 13
    Staging Deployment
    Deploy MVP to pre-production environment for final validation
    2 days
  14. 14
    Stakeholder Review
    Final stakeholder approval before production deployment
    2 days
  15. 15
    Production Deployment
    Launch MVP on live servers with monitoring setup
    3 days
  16. 16
    Project Complete
    Deliver MVP with documentation and post-mortem review
    Milestone

Who This Is For

Startup founders and product managers use this template to bring a web application from concept to launch in approximately 45 days. It covers the full lifecycle from stakeholder interviews and UX design through parallel front-end and back-end development to production deployment.

Why Use LoopGantt

Building an MVP requires constant reprioritization as you learn from user feedback. LoopGantt lets you drag tasks to reorder phases, instantly see how changes affect your launch date, and share a live timeline with investors and stakeholders.

Related Templates

Ready to Start?

Load this template into LoopGantt and customize it for your project.

Use This Template