Web Application MVP Template
Build a minimum viable product web application from scratch
What's Included
This template contains 16 tasks with built-in dependencies, milestones, and realistic duration estimates. Each task includes a description so your team knows exactly what needs to happen.
- 1Project KickoffAlign stakeholders on MVP scope, requirements, and success criteriaMilestone
- 2Discovery PhaseConduct stakeholder interviews, define MVP scope, create user stories, and complete competitor analysis5 days
- 3UI/UX DesignCreate wireframes, user flows, and interactive mockups for core features1 week
- 4Design Review & ApprovalPresent and finalize design assets with stakeholders2 days
- 5Front-End DevelopmentImplement client-side interfaces using HTML/CSS/JavaScript framework6 days
- 6Back-End DevelopmentDevelop server-side logic, APIs, and database architecture6 days
- 7System IntegrationConnect front-end with back-end, implement core feature integrations3 days
- 8Development ReviewVerify completion of MVP development phaseMilestone
- 9Unit TestingExecute unit tests for both front-end and back-end components3 days
- 10Integration TestingVerify cross-component functionality and API interactions3 days
- 11User Acceptance Testing (UAT)Conduct stakeholder testing with real user scenarios4 days
- 12Bug Fixing & QAResolve issues identified in testing phases5 days
- 13Staging DeploymentDeploy MVP to pre-production environment for final validation2 days
- 14Stakeholder ReviewFinal stakeholder approval before production deployment2 days
- 15Production DeploymentLaunch MVP on live servers with monitoring setup3 days
- 16Project CompleteDeliver MVP with documentation and post-mortem reviewMilestone
Who This Is For
Startup founders and product managers use this template to bring a web application from concept to launch in approximately 45 days. It covers the full lifecycle from stakeholder interviews and UX design through parallel front-end and back-end development to production deployment.
Why Use LoopGantt
Building an MVP requires constant reprioritization as you learn from user feedback. LoopGantt lets you drag tasks to reorder phases, instantly see how changes affect your launch date, and share a live timeline with investors and stakeholders.